General Contractor for a 101-unit apartment and commercial building. 2 levels of above ground parking and commercial in concrete, plus 4 stories of wood frame structure. Interesting feature includes a road breeze-way through the building to provide access to the school behind.
STATUS
2018-10-06: Construction underway with the extensive ground improvements nearly complete.
2019-04-16: The project is currently at framing
2019-08-25: Fly the precast bridge in to place to connect both buildings
2019-11-15: Roofing under way
2019-12-15: Installing plumbing, Electrical, Sprinkler Rough In’s
2020-01-15: Building Wrap in progress
2020-02-15: CRU store front glazing being installed
2020-03-15: Siding and architectural build-outs in progress
2020-04-15: Electrical, mechanical, sprinkler Rough In’s complete.
2020-05-15: Drywall starts in the suites
2020-06-15: Mud and Taping underway in suites
2020-07-16: Offsite Civil starts
2020-08-20: School access and sidewalks are installed
2020-09-15: Finishing in the suites are underway
2020-10-12: Prep for homeowner walk through
2020-11-05: First homeowner orientation start