Start Date
2017

Location
Kelowna, BC
Units
427 Condos, Townhomes and Live/Work Units. 30,000 sf of commercial retail space

Development management and construction of 36-storey and 29-storey high-rises in Kelowna, with development in partnership with North American Development Group.

The luxury residential and retail at ONE Water Street are just steps from Okanagan Lake and in the heart of downtown Kelowna. This collection of condominiums, townhomes, penthouses, and live-work homes features elegant finishes, and residents have access to an unparalleled indoor and outdoor amenity podium. ONE Water Street is Okanagan Urban Living.

Visit Website

STATUS

2017-09-13: Presentation centre opened mid-August 2017. Sales launch day scheduled for September 29 and 30. Construction anticipated to commence Spring 2018.

2018-10-06: Construction well underway on both towers. Vertical walls and columns on Level 1 of Tower 1 nearing completion, and slab-on-grade being installed. Piling for Tower 2 getting wrapped up.

2019-04-02: Construction is right on schedule, with the second crane now on site as the levels are climbing higher. Okanagan Edge media release Second Crane at ONE Water Street.

2019-09-12: East Tower is taking shape, with construction at the 12th Level and windows being installed on the 4th Level. West Tower construction has the ground-floor structure complete and the 2nd Level is underway.

2019-11-18: East Tower is halfway up at 18 stories. West Tower construction has the ground-floor structure complete and the 2nd Level is underway.

2020-04-03: East Tower is over the 30th story mark and the structure of the parkade and bench are almost complete

2020-06-01: Forming of the 35th floor with windows going in on level 25.  The transition pour was in early May and the foot print for the entire podium is now complete

2020-07-01: East Tower Top toping up this month and getting ready to start going vertical on West Tower shortly.

2020-08-01: East Tower windows being installed on level 30 and steel stud install and level 29. Pool construction ready for concrete on The Bench and Podium roofing in preparation for landscaping work.

2020-10-01:  We are already drywalling the 32nd floor and appliances are getting installed on the 18th floor. Finishing level 37 with installing the mechanical units.  We have gone vertical on the West Tower with Level 7 poured and getting everything prepped for level 8 this week.

2020-11-01: Tower 1 – Crane and Temporary elevator coming down early December with operational permanent elevators finishing up and crane will be transitioning to West Tower. Tower 2 – forming level 11 with prep work for window installation starting. Podium – family pool being formed, lap pool poured and pickleball court and landscaping beginning.

2020-12-01: East Tower – elevators nearly complete so that crane can be removed mid December and window installation on the 36th floor. West Tower – level 13 poured and starting window installation on the lower floors.

2021-01-01: East Tower – Crane has been removed and elevators are complete helping with homeowner orientations that have started this month.  Lobby work progressing as well as the commercial/retail spaces.  West Tower – Crane has been installed and  level 15 is poured.