Kerkhoff is acting as the Development and General Contractor for a 4 storey residential wood frame rental condominium. This apartment building with 59 rental has over 2 levels above grade parkade with extensive outdoor fully landscaped patio areas on levels 2 & 3.
STATUS
2019-11-22 – Site ground work is in progress
2019-12-15 – Off Site utility works are well underway with the road and boulevard improvements schedule for the summer of 2020
2010-11-01 – On site utilities are complete with permanent power expected in the next several weeks
2019-11-01 – Concrete foundation work is underway with 70% of the two level parkade now complete and the entire foundation work expected to be completed early May 2020
2020-03-15 – Wood Framing of the main floor townhouse’s is underway with the upper condo levels expected to begin in May 2020
2020-04-03 – Forming and framing is underway
2020-06-01 – Wood framing of the main floor townhouse’s and upper condo level 4 complete and level 5 walls starting. Road & boulevard improvements scheduled for summer
2020-07-01 – Roofing will be starting this month
2020-08-01 – Concrete foundation at 99% complete with 4th level concrete floor topping complete. HVAC & electrical finishing and interior insulation to begin
2020-09-21 Off Site utility works are complete providing permanent power, water, sewer and natural gas to the building with the road and boulevard improvements schedule for the fall of 2020
2020-09-21 Concrete foundation work, concrete wall grinding and sacking 100% in preparation for exterior painting
2020-09-21 Siding installation underway
2020-09-21 Townhouse’s drywalled and into taping
2020-09-21 Condo units plumbing, HVAC and Electrical rough in are at 95% complete
2020-09-21 All Concrete Floor topping has been placed on the upper floors
2020-09-21 Exterior Door and Window installation is 100% complete
2020-09-21 Wood Framing is 100% complete with roofing at 90% complete. Building is 100% water tight
2020-09-21 Townhouse and Condo show suites completion expected for early November 2020
2020-11-01 – Town home show suite ready and registrations for rental opportunities available through the website. Building exterior door and window installations complete, and HVAC, plumbing and electrical rough-ins finalizing.
2020-12-01 – Site utility works complete providing permanent power, water, sewer and natural gas to the building. Level 3 cabinet and finish carpentry, level 4 prime painting, level 5 drywall taping, level 6 drywall installation.
2021-01-01 – cabinet install and finish carpentry complete on level 3 with final paint on goin, level 4 into paint priming, level 5 drywall is complete, level 6 into taping. New Jr 2 bedroom show suite staging complete with Matterport video and pictures scheduled.