Development management and construction of 66 town-homes and all associated on-site and off-site servicing and road construction. Nestled on the hillside in Chilliwack, the exclusive community stands apart in every way. The elevated setting is private and peaceful, yet close to everything you need for a perfect ‘lock and go’ lifestyle.

Visit Website

STATUS

2016-02-19 – Construction has completed on the first 12 units. The next phase of 10 units are anticipated to commence Spring 2017.

2016-11-02 – Next phase (8 units) now expected to commence mid-2017. Overall civil design for the site in progress.

2017-09-13 – Construction well underway on phases 3 and 4, bringing an additional 16 units to the market, with completion of these phases anticipated by Spring 2018. Pre-sales have been advancing well.

2019-05-01 – Construction of Phase 5 is underway with the first 2 units framed and getting ready for drywall install.

2020-03-31 – all 8 units are complete and available for viewing. Visit our website for more info.