The Packing District

Start Date
June 2019

Location
Kelowna, BC
Units
158 apartment units and 19,186 of commercial space

General Contractor for 2 buildings totaling 158 apartment units and 19,186 square feet of commercial space with an estimated completion date of December 2020.

STATUS

2019-05-27 Starting excavation of site

2019-09-12 Construction of both buildings are taking shape very nicely

2020-02-01 Exterior finishes have been underway for several months with the final hardie board siding being installed

2020-12-01 Interior finishes are well under way including cabinets, tile, flooring and finishing trims

2020-04-01 Exterior brick finish is now underway

2020-04-20 Site works to begin including site grading, parking lot paving and landscaping

2020-06-01 – Exterior finishes are 85% complete, while interior finishes are starting to finalize as well as landscaping and paving of the site

2020-07-01 – Suite energization will be starting mid July for both buildings

2020-08-01 – Exterior finished are 90% complete including patio deck railings. Interior finished are being finalized with the 1st building complete in September 2020.

2020-10-01 – Building 1 has been turned over and leased up.  Building 2 is coming along with interior finishes and exterior finishes such as brick work, parking lot paving and landscaping

2020-11-01 – Parking lot is complete and landscaping finishes underway.  Interior finishes in building 2 finalizing with touchups and completing hallways and corridors.

2020-12-01 – Building 2 on schedule for occupancy mid December with Final Mechanical & Electrical inspections beginning of December. Parking lot paving finalized and landscaping in the last stages.

2020-12-08 – Final Occupancy has been received for Building 2!  Congratulations to the team for the completion of both buildings at Packing District!

2021-01-27  – Achieved Occupancy of Building 1 on September 1 with 100% of residents now moved into their units.  Building 2 Occupancy received December 8, 2020 with move in’s at 75%

2021-01-27  – Exterior Wood Trellis 100% complete

2021-01-27  – On and Off site Landscaping; Shrub, Tree & Irrigation installation at 98%